South side of E. Newport Pike, east side of Marsh Lane, west side of Forest Drive. Demolish existing restaurant and construct a 7,225 s.f. retail facility and site improvements. CN Zoning. CD 1. Christiana Hundred.
VOULTSIS PETROS & CATHERINE
RECORDED/RESOLV
BRADFORD S SHOCKLEY
STACY M MCNATT

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Board Recommendations and Input

+
  Legal Agreements and Documents

+
  Miscellaneous Documents

+
  Plans

Subdivision Land Development

Planning

No
10/3/2013
9/24/2014

Ground Floor Area

7225
0
7225
7225

Acres

0.44
0.32
0.93
0
0

Non-residential Lots

1
1

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1483860 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1483861 RELEASE OF BONDS Not Available Incomplete Not Available
1483862 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
9/16/2013 NON RES SWM FACILITY MAINT FUND Paid $4,800.00
9/16/2013 EXPLORATORY SKETCH PLAN FEE Paid $750.00
9/16/2013 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
10/17/2013 PLANNING RESUBMISSION FEE Paid $750.00
2/11/2014 NONRESIDENTIAL GRADING PLAN REVIEW Paid $750.00
2/11/2014 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $405.00
4/1/2014 (ENG) MINOR REVIEW FEE Paid $250.00
4/14/2014 AGREEMENT FEE Paid $250.00
9/16/2014 MINOR RECORD PLAN FEE (NONRES LAND DEV) Paid $4,084.00
10/6/2014 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
9/16/2013 DELDOT APPROVAL LETTER 7/15/2014 APPROVED
9/16/2013 FIRE MARSHAL APPROVAL RCV'D 4/2/2014 APPROVED
9/16/2013 WATER CERTICATION RECEIVED 1/14/2014 APPROVED
9/16/2013 SIGNED AFFIDAVIT FOR POSTING 10/3/2013 APPROVED
2/11/2014 NOI CONFIRMATION RECEIVED 8/4/2014 APPROVED
9/16/2014 PLAN RECORDATION 10/6/2014 APPROVED
9/16/2014 RECORDER OF DEEDS FEE RECEIVED 9/22/2014 APPROVED
9/16/2014 GENERAL MANAGER RECRD PLAN APR 10/6/2014 APPROVED
9/16/2014 LAND DEV IMPROV AGREE RECORDED 9/22/2014 APPROVED
10/6/2014 OUTFALL DATA SHEET RECEIVED Not Available
10/6/2014 SANITARY SEWER Not Available

Reviews

Review Type Status
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
ENG: EXPLORATORY REVIEW Conditional Approval
PRELIMINARY TRAFFIC ANALYSIS Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
EXPLORATORY REVIEW BY PLANNING Denied
INITIAL MAPPING REVIEW Approved
EXPLORATORY REVIEW BY PLANNING Waived
ENG: EXPLORATORY REVIEW Conditional Approval
PLANNING CONSTRUCTION PLAN RVW Waived
MAINTENANCE DECLARATION REVIEW Conditional Approval
LANDSCAPE PLAN REVIEW Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Approved
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN REVIEW Approved
RECORD PLAN SUBMISSION Approved
FINAL MAPPING REVIEW Approved
ENGINEERING CONSTRUCTION PLAN Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
AS-BUILT FOR STORM WATER MNGMT Incomplete