river photo
Home > Land Use > Project Search > Project Details

Project # 20130561

SUBDIVISION LAND DEVELOPMENT
North side of Breidablik Drive, 625 feet east from terminus of Breidablik Drive. Revise lot lines on existing lots. NC2A zone, CD 2
PETTINARO VERINO & KATHRYN TRUSTEE
RECORDED/RESOLV
Steven E. Faux
JOHN GYSLING

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Legal Agreements and Documents

+
  Miscellaneous Documents

+
  Plans

Subdivision Land Development

Planning

No
8/15/2013
10/22/2013

Ground Floor Area

0
0
0
0

Acres

0
0
0
0
0

Residential Lots

3
3

Acreage

9
9

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1385727 OPEN SPACE INSP (RESIDENTIAL) Not Available Incomplete Not Available
1385728 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1385729 RELEASE OF BONDS Not Available Incomplete Not Available
1385730 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available
1385731 ENGINEERING OPEN SPACE AT 50 Not Available Incomplete Not Available
1385732 ENGINEERING OPEN SPACE AT 75 Not Available Incomplete Not Available
1385733 ENGINEERING OPEN SPACE AT 90 Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
8/15/2013 EXPLORATORY SKETCH PLAN FEE Paid $750.00
8/15/2013 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
9/30/2013 (ENG) MINOR REVIEW FEE Paid $250.00
9/30/2013 MINOR RECORD PLAN FEE (RESUB) Paid $2,500.00
10/28/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
8/15/2013 DELDOT APPROVAL LETTER 10/11/2013 APPROVED
8/15/2013 FIRE MARSHAL APPROVAL RCV'D 9/30/2013 APPROVED
9/30/2013 RECORDER OF DEEDS FEE RECEIVED 10/1/2013 RECEIVED
9/30/2013 COASTAL ZONE APPROVAL 10/1/2013 NOT APPLICABLE
9/30/2013 SUBAQUEOUS LANDS PERMIT 10/1/2013 NOT APPLICABLE
9/30/2013 ARMY CORPS PERMIT APPROVED 10/1/2013 NOT APPLICABLE
9/30/2013 CRITICAL NATURAL AREA APPROVAL 10/1/2013 NOT APPLICABLE
9/30/2013 GENERAL MANAGER RECRD PLAN APR 10/28/2013 APPROVED
9/30/2013 PLAN RECORDATION 10/28/2013 APPROVED
9/30/2013 OFFICE OF AERONAUTICS APPROVAL 10/1/2013 NOT APPLICABLE
10/28/2013 OUTFALL DATA SHEET RECEIVED Not Available
10/28/2013 SANITARY SEWER Not Available

Reviews

Review Type Status
PRELIMINARY TRAFFIC ANALYSIS Approved
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
INITIAL MAPPING REVIEW Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
ENG: EXPLORATORY REVIEW Approved
EXPLORATORY REVIEW BY PLANNING Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
PLANNING CONSTRUCTION PLAN RVW Approved
ENGINEERING CONSTRUCTION PLAN Approved
LANDSCAPE PLAN REVIEW Conditional Approval
RECORD PLAN SUBMISSION Approved
FINAL MAPPING REVIEW Conditional Approval
RECORD PLAN REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
AS-BUILT FOR STORM WATER MNGMT Incomplete