SUBDIVISION LAND DEVELOPMENT
East side of Route 1 north at Lower Twin Lane Road, subdivide tax parcel 12-007.00-024 into two parcels. HI Zoning. CD 12. Red Lion Hundred
DELAWARE CITY REFINING COMPANY LLC
RECORDED/RESOLV
ANTONI SEKOWSKI
MIKE ANDREW CLENDANIEL

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Studies, Reports and Data

+
  Miscellaneous Documents

+
  Procedural Documents

+
  Plans

Subdivision Land Development

Planning

No
6/25/2013
9/27/2013

Ground Floor Area

0
0
0
0

Acres

0
0
0
0
0

Non-residential Lots

2
2

Acreage

254
254

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1378126 OPEN SPACE INSP (RESIDENTIAL) Not Available Incomplete Not Available
1378127 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1378128 RELEASE OF BONDS Not Available Incomplete Not Available
1378129 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available
1378130 ENGINEERING OPEN SPACE AT 50 Not Available Incomplete Not Available
1378131 ENGINEERING OPEN SPACE AT 75 Not Available Incomplete Not Available
1378132 ENGINEERING OPEN SPACE AT 90 Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
6/10/2013 EXPLORATORY SKETCH PLAN FEE Paid $750.00
6/10/2013 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
8/1/2013 (ENG) MINOR REVIEW FEE Paid $250.00
8/1/2013 MINOR RECORD PLAN FEE (NON RES SUBDIV) Paid $3,300.00
10/1/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
6/10/2013 WATER CERTICATION RECEIVED 8/7/2013 COMPLETED
6/10/2013 FIRE MARSHAL APPROVAL RCV'D 9/3/2013 COMPLETED
6/10/2013 DELDOT APPROVAL LETTER 9/13/2013 COMPLETED
7/2/2013 NOI CONFIRMATION RECEIVED 8/1/2013 NOT APPLICABLE
8/7/2013 GENERAL MANAGER RECRD PLAN APR 10/1/2013 APPROVED
8/7/2013 COASTAL ZONE APPROVAL 8/7/2013 NOT APPLICABLE
8/7/2013 ARMY CORPS PERMIT APPROVED 8/7/2013 NOT APPLICABLE
8/7/2013 PLAN RECORDATION 10/1/2013 APPROVED
8/7/2013 RECORDER OF DEEDS FEE RECEIVED 8/7/2013 COMPLETED
10/1/2013 SANITARY SEWER Not Available
10/1/2013 OUTFALL DATA SHEET RECEIVED Not Available

Reviews

Review Type Status
ENVIRONMENTAL IMPACT ASSESSMNT Approved
ENG: EXPLORATORY REVIEW Approved
HISTORIC REVIEW EXPLORATORY Approved
INITIAL MAPPING REVIEW Conditional Approval
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
SEWER CAPACITY AT EXPLORATORY Approved
EXPLORATORY REVIEW BY PLANNING Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
MAINTENANCE DECLARATION REVIEW Conditional Approval
PLANNING CONSTRUCTION PLAN RVW Approved
ENGINEERING CONSTRUCTION PLAN Approved
LANDSCAPE PLAN REVIEW Conditional Approval
RECORD PLAN SUBMISSION Approved
FINAL MAPPING REVIEW Approved
RECORD PLAN REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
AS-BUILT FOR STORM WATER MNGMT Incomplete