Project # 20130383

SUBDIVISION LAND DEVELOPMENT
East side of Centerville Road, 550 feet north of Lancaster Pike. Subdivide tax parcels 07-028.40-026 and -027 into two lots each. NC15 Zoning. CD 2. Christiana Hundred
OSBORNE BRUCE E & CYNTHIA M
Withdrawn
BRADFORD S SHOCKLEY
STACY M MCNATT

+
  Applicant's Submissions and Correspondence

+
  Planning Review Reports

+
  Plans

Subdivision Land Development

Planning

No
6/19/2013
Not Available

Ground Floor Area

0
0
0
0

Acres

0
0
0
0
0

Residential Lots

4
4

Acreage

3
3

Fees

Date Applied Description Status Amount
5/28/2013 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
5/28/2013 EXPLORATORY SKETCH PLAN FEE Paid $750.00
6/25/2013 RESIDENTIAL GRADING PLAN REVIEW Unpaid $500.00
6/25/2013 (ENG) STORM WATER MANAGEMENT E&S FEE-RES Unpaid $375.00

Conditions

Application Date Description Action Date Action Description
5/28/2013 SIGNED AFFIDAVIT FOR POSTING 6/19/2013 APPROVED
5/28/2013 DEVLOPERS AFFIDAVIT Not Available
5/28/2013 FIRE MARSHAL APPROVAL RCV'D Not Available
5/28/2013 WATER CERTICATION RECEIVED Not Available
5/28/2013 DELDOT APPROVAL LETTER Not Available
5/28/2013 REQ PER SEC 10.3.4.4 OF DSSR Not Available
6/25/2013 NOI CONFIRMATION RECEIVED Not Available

Reviews

Review Type Status
OS REVIEW AT EXPLOR SPEC SERV Approved
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
PRELIMINARY TRAFFIC ANALYSIS Approved
INITIAL MAPPING REVIEW Conditional Approval
EXPLORATORY REVIEW BY PLANNING Conditional Approval
ENG: EXPLORATORY REVIEW Approved
MAINTENANCE DECLARATION REVIEW Incomplete
LANDSCAPE PLAN REVIEW Incomplete
ENGINEERING CONSTRUCTION PLAN Incomplete
PLANNING CONSTRUCTION PLAN RVW Incomplete