river photo
Home > Land Use > Project Search > Project Details

Project # 20120865

SUBDIVISION LAND DEVELOPMENT
Southwest side of Church Road, south of CSX railroad. Resubdivide lots 522, 522A, 342-373 and community open space. ST Zoning. CD 12. New Castle Hundred
REYBOLD VENTURE GROUP X1-D LLC
RECORDED/RESOLV
Michael J. Bennett
JOHN GYSLING

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Plans

Subdivision Land Development

Planning

No
12/7/2012
2/21/2013

Ground Floor Area

0
0
0
0

Acres

0
0
0
0
0

Residential Lots

84
120
353
220
777

Acreage

174
174

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1312615 OPEN SPACE INSP (RESIDENTIAL) Not Available Incomplete Not Available
1312616 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1312617 RELEASE OF BONDS Not Available Incomplete Not Available
1312618 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
12/10/2012 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
12/10/2012 EXPLORATORY SKETCH PLAN FEE Paid $750.00
1/14/2013 (ENG) MINOR REVIEW FEE Paid $250.00
1/14/2013 (ENG) GENERAL DEVELOPMENT NON RES FEE Paid $750.00
1/14/2013 MINOR RECORD PLAN FEE (RESUB) Paid $2,500.00
2/6/2013 (ENG) SEWER PLAN FEE Paid $750.00
2/6/2013 (LDIA) SEWER INSPECTION FEE Paid $212.50
2/25/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
12/10/2012 DELDOT APPROVAL LETTER 1/14/2013 APPROVED
12/10/2012 FIRE MARSHAL APPROVAL RCV'D 1/14/2013 APPROVED
1/14/2013 NOI CONFIRMATION RECEIVED 1/14/2013 APPROVED
1/14/2013 GENERAL MANAGER RECRD PLAN APR 2/20/2013 APPROVED
1/14/2013 RECORDER OF DEEDS FEE RECEIVED 2/8/2013 RECEIVED
1/14/2013 PLAN RECORDATION 2/25/2013 APPROVED
2/25/2013 OUTFALL DATA SHEET RECEIVED Not Available
2/25/2013 SANITARY SEWER Not Available

Reviews

Review Type Status
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Approved
INITIAL MAPPING REVIEW Conditional Approval
ENG: EXPLORATORY REVIEW Approved
PRELIMINARY TRAFFIC ANALYSIS Approved
EXPLORATORY REVIEW BY PLANNING Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
ENGINEERING CONSTRUCTION PLAN Approved
PLANNING CONSTRUCTION PLAN RVW Approved
LANDSCAPE PLAN REVIEW Approved
FINAL MAPPING REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN SUBMISSION Approved
RECORD PLAN REVIEW Approved
SPEC SERV FINAL SEWER REVIEW Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
AS-BUILT FOR STORM WATER MNGMT Incomplete