river photo
Home > Land Use > Project Search > Project Details

Project # 20120841

SUBDIVISION LAND DEVELOPMENT
North side of Old Capitol Trail, directly across from School Lane. Reconfigure previously approved flex warehouse facility and parking. I Zoning. CD 1. Christiana Hundred
MARSHALLTON COMMERCE CENTER LLC
RECORDED/RESOLV
MATTHEW ROGERS
JOHN GYSLING

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Studies, Reports and Data

+
  Legal Agreements and Documents

+
  Plans

Subdivision Land Development

Planning

No
12/3/2012
3/14/2014

Ground Floor Area

49995
49995
0
49995

Acres

1.75
2.51
5.41
0
0

Non-residential Lots

1
1

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1417311 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1417312 RELEASE OF BONDS Not Available Incomplete Not Available
1417313 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
12/3/2012 EXPLORATORY SKETCH PLAN FEE Paid $750.00
12/3/2012 (ENG) MINOR EXPLORATORY SKETCH PLAN FEE Paid $500.00
1/16/2013 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $1,470.00
1/16/2013 NONRESIDENTIAL GRADING PLAN REVIEW Paid $750.00
5/17/2013 (ENG) SEWER PLAN FEE Paid $1,500.00
5/20/2013 AGREEMENT FEE Paid $250.00
5/20/2013 MINOR RECORD PLAN FEE (RESUB) Paid $4,000.00
3/5/2014 (ENG) MINOR REVIEW FEE Paid $250.00
3/18/2014 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
12/3/2012 DELDOT APPROVAL LETTER 2/27/2014 APPROVED
12/3/2012 FIRE MARSHAL APPROVAL RCV'D 3/5/2014 APPROVED
12/3/2012 WATER CERTICATION RECEIVED 2/27/2014 NOT APPLICABLE
12/3/2012 REQ PER SEC 10.3.4.4 OF DSSR 12/14/2012 APPROVED
1/16/2013 NOI CONFIRMATION RECEIVED 2/27/2014 APPROVED
3/5/2014 ARMY CORPS PERMIT APPROVED 3/5/2014 NOT APPLICABLE
3/5/2014 OFFICE OF AERONAUTICS APPROVAL 3/5/2014 NOT APPLICABLE
3/5/2014 PLAN RECORDATION 3/18/2014 APPROVED
3/5/2014 SUBAQUEOUS LANDS PERMIT 3/5/2014 NOT APPLICABLE
3/5/2014 CRITICAL NATURAL AREA APPROVAL 3/5/2014 NOT APPLICABLE
3/5/2014 RECORDER OF DEEDS FEE RECEIVED 3/5/2014 COMPLETED
3/5/2014 COASTAL ZONE APPROVAL 3/5/2014 NOT APPLICABLE
3/5/2014 GENERAL MANAGER RECRD PLAN APR 3/18/2014 APPROVED
3/18/2014 OUTFALL DATA SHEET RECEIVED Not Available
3/18/2014 SANITARY SEWER Not Available

Reviews

Review Type Status
PRELIMINARY TRAFFIC ANALYSIS Approved
HISTORIC REVIEW EXPLORATORY Approved
EXPLORATORY REVIEW BY PLANNING Conditional Approval
OS REVIEW AT EXPLOR SPEC SERV Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
INITIAL MAPPING REVIEW Approved
ENG: EXPLORATORY REVIEW Conditional Approval
LANDSCAPE PLAN REVIEW Approved
PLANNING CONSTRUCTION PLAN RVW Approved
ENGINEERING CONSTRUCTION PLAN Approved
SPEC SERV FINAL SEWER REVIEW Approved
ENGINEERING CONSTRUCTION PLAN Approved
RECORD PLAN SUBMISSION Approved
TRAFFIC REVIEW AT RECORDATION Approved
FINAL MAPPING REVIEW Approved
RECORD PLAN REVIEW Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
AS-BUILT FOR STORM WATER MNGMT Incomplete