river photo
Home > Land Use > Project Search > Project Details

Project # 20120715

SUBDIVISION LAND DEVELOPMENT
East side of Route 1, south side of School House Road. Proposed loop rail track unloading facility, 1920 s.f. buildings and associated parking. HI Zoning. CD 12. Red Lion Hundred
DELAWARE CITY REFINING COMPANY LLC
RECORDED/RESOLV
ANTONI SEKOWSKI
MIKE ANDREW CLENDANIEL

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Miscellaneous Documents

+
  Plans

Subdivision Land Development

Planning

No
10/12/2012
12/6/2012

Ground Floor Area

2330
0
2330
2330

Acres

10.82
134.31
145.18
0
0

Non-residential Lots

1
1

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1293544 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1293545 RELEASE OF BONDS Not Available Incomplete Not Available
1349975 FIELD INSPECTION OF FACILITIES Not Available Passed 6/27/2013
1349976 FIELD INSPECTION OF FACILITIES Not Available Passed 9/24/2013

Fees

Date Applied Description Status Amount
10/23/2012 PARKING PLAN FEE Paid $1,500.00
10/23/2012 (ENG) GENERAL DEVELOPMENT NON RES FEE Paid $1,500.00
10/23/2012 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $11,475.00
10/23/2012 STORMWATER AS-BUILT PLAN REVIEW FEE Paid $250.00
11/16/2012 NON RES SWM FACILITY MAINT FUND Paid $14,400.00
2/7/2013 ENGINEERING RESUBMISSION FEE Paid $750.00
6/19/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Paid $250.00

Conditions

Application Date Description Action Date Action Description
10/23/2012 FIRE MARSHAL APPROVAL RCV'D 12/6/2012 COMPLETED
10/23/2012 WATER CERTICATION RECEIVED 10/31/2012 COMPLETED
10/23/2012 DELDOT APPROVAL LETTER 12/6/2012 COMPLETED
11/27/2012 NOI CONFIRMATION RECEIVED 11/28/2012 COMPLETED
12/6/2012 OUTFALL DATA SHEET RECEIVED Not Available
12/6/2012 SANITARY SEWER Not Available

Reviews

Review Type Status
ENG: EXPLORATORY REVIEW Conditional Approval
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Approved
PRELIMINARY TRAFFIC ANALYSIS Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
EXPLORATORY REVIEW BY PLANNING Conditional Approval
INITIAL MAPPING REVIEW Conditional Approval
PLANNING CONSTRUCTION PLAN RVW Approved
LANDSCAPE PLAN REVIEW Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Approved
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN REVIEW Approved
RECORD PLAN SUBMISSION Approved
ENGINEERING CONSTRUCTION PLAN Approved
AS-BUILT FOR STORM WATER MNGMT Conditional Approval
AS-BUILT FOR STORM WATER MNGMT Conditional Approval
AS-BUILT FOR STORM WATER MNGMT Approved