Project # 20120694

SUBDIVISION LAND DEVELOPMENT
South side of Kirkwood Highway, approximately 300 feet east of Woodhaven Drive. Expansion of 20,778 square foot mezzanine storage area. CR Zoning. CD 9. Mill Creek Hundred.
DELAWARE ECONOMIC DEV AUTH
RECORDED/RESOLV
ANTONI SEKOWSKI
JOHN GYSLING

Subdivision Land Development

Planning

No
11/7/2012
4/10/2013

Ground Floor Area

19610
19999
779
20778

Acres

0.88
0.68
2.01
0
0

Non-residential Lots

1
1

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1324001 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1324002 RELEASE OF BONDS Not Available Incomplete Not Available
1324003 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
10/16/2012 (ENG) MAJOR EXPLORATORY SKETCH PLAN FEE $1,000.00
10/16/2012 EXPLORATORY SKETCH PLAN FEE $1,000.00
10/16/2012 NON RES SWM FACILITY MAINT FUND Unpaid $1.00
3/6/2013 AGREEMENT FEE $0.00
3/6/2013 (ENG) MAJOR RECORD PLAN REVIEW $2,060.00
3/6/2013 MAJOR RECORD PLAN FEE (NONRES LAND DEV) $5,155.80
4/11/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
10/16/2012 WATER CERTICATION RECEIVED 3/6/2013 COMPLETED
10/16/2012 SIGNED AFFIDAVIT FOR POSTING 11/8/2012 COMPLETED
10/16/2012 PRE-APPLICATION CONFERENCE 11/8/2012 COMPLETED
10/16/2012 FINAL PLUS 3/6/2013 COMPLETED
10/16/2012 DELDOT APPROVAL LETTER 3/25/2013 APPROVED
10/16/2012 FIRE MARSHAL APPROVAL RCV'D 3/20/2013 APPROVED
3/6/2013 COUNTY COUNCIL REC PLAN APPROV 4/11/2013 APPROVED
3/6/2013 PLAN RECORDATION 4/11/2013 APPROVED
3/6/2013 RECORDER OF DEEDS FEE RECEIVED 3/25/2013 APPROVED
3/6/2013 LAND DEV IMPROV AGREE RECORDED 3/20/2013 COMPLETED
3/6/2013 GENERAL MANAGER RECRD PLAN APR 3/25/2013 APPROVED
4/11/2013 SANITARY SEWER Not Available
4/11/2013 OUTFALL DATA SHEET RECEIVED Not Available
4/11/2013 MONUMENT CERTIFICATION Not Available

Reviews

Review Type Status
INITIAL MAPPING REVIEW Approved
EXPLORATORY REVIEW BY PLANNING Approved
PRELIMINARY TRAFFIC ANALYSIS Approved
ENG: EXPLORATORY REVIEW Approved
SEWER CAPACITY AT EXPLORATORY Approved
TRAFFIC COMPLIANCE REVIEW Approved
ENINEERING PRE-APPLICATON RVW Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
SEWER DESIGN AT EXPLORATORY Waived
HISTORIC REVIEW EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
RECORD PLAN REVIEW Approved
FINAL MAPPING REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN SUBMISSION Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
INITIATE OPEN SPACE TURNOVER Incomplete
NOTIFY APPLICANT PROJECT @ 50% Incomplete
AS-BUILT FOR STORM WATER MNGMT Incomplete
NOTIFY APPLICANT PROJECT @ 90% Incomplete
SWM ASBUILT APRVL BY NCC ENG Incomplete
NOTIFY APPLICANT PROJECT @ 75% Incomplete