North side of Hay Road, south of Norfolk Southern Railroad, 150 feet east of Exit 4 of I495. Construct two asphalt storage tanks, truck scale, stone crusher, hot oil heating building and additional roadway infrastructure for loading and unloading. HI Zoning. CD 8. Brandywine Hundred.
IKO PRODUCTION INC
Active
ANTONI SEKOWSKI
JOHN GYSLING

+
  Applicant's Submissions and Correspondence

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Miscellaneous Documents

+
  Plans

Subdivision Land Development

Planning

No
4/10/2012
Not Available

Ground Floor Area

115892
115162
800
115962

Acres

8.7
1.4
12.76
0
0

Non-residential Lots

1
1

Fees

Date Applied Description Status Amount
4/11/2012 SITE PLAN FEE Paid $1,500.00
4/11/2012 (ENG) GENERAL DEVELOPMENT NON RES FEE Paid $750.00
4/11/2012 (ENG) STORM WATER MANAGEMENT E&S FEE Refunded $1,125.00
4/17/2012 ENGINEERING INCOMPLETE PLAN SUBMISSION Paid $250.00
4/20/2012 PLANNING RESUBMISSION FEE Paid $750.00
9/23/2013 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $600.00
9/23/2013 (ENG) MINOR REVIEW FEE Paid $250.00
10/9/2013 PLANNING RESUBMISSION FEE Unpaid $750.00
12/16/2013 NON RES SWM FACILITY MAINT FUND Unpaid $6,400.00

Conditions

Application Date Description Action Date Action Description
4/11/2012 REQ PER SEC 10.3.4.4 OF DSSR 4/17/2012 REPORT ISSUED
4/11/2012 WATER CERTICATION RECEIVED Not Available
4/11/2012 DELDOT APPROVAL LETTER Not Available
4/11/2012 FIRE MARSHAL APPROVAL RCV'D Not Available

Reviews

Review Type Status
OS REVIEW AT EXPLOR SPEC SERV Approved
SEWER CAPACITY AT EXPLORATORY Approved
HISTORIC REVIEW EXPLORATORY Approved
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
ENVIRONMENTAL IMPACT ASSESSMNT Incomplete
EXPLORATORY REVIEW BY PLANNING Denied
ENG: EXPLORATORY REVIEW Waived
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Incomplete