Project # 20120154

SUBDIVISION LAND DEVELOPMENT
West side of Summit Bridge Road, 2,000 feet south of Porter Road. Create an open spaced planned subdivision consisting of 150 single family detached, semi-detached, and townhouse lots. S Zoning. CD 6. Pencader Hundred.
HARRISON THOMAS C F
Active
Steven E. Faux
STACY M MCNATT

Subdivision Land Development

Planning

No
9/18/2012
Not Available

Ground Floor Area

0
0
0
0

Acres

0
0
0
0
0

Residential Lots

48
28
74
150

Acreage

87
22
8
117

Fees

Date Applied Description Status Amount
3/20/2012 (ENG) MAJOR EXPLORATORY SKETCH PLAN FEE $1,000.00
3/20/2012 EXPLORATORY SKETCH PLAN FEE $1,000.00

Conditions

Application Date Description Action Date Action Description
3/20/2012 SIGNED AFFIDAVIT FOR POSTING 10/3/2012 RECEIVED
3/20/2012 PRE-APPLICATION CONFERENCE 10/3/2012 COMPLETED
3/20/2012 WATER CERTICATION RECEIVED Not Available
3/20/2012 COASTAL ZONE APPROVAL Not Available
3/20/2012 DEVLOPERS AFFIDAVIT Not Available
3/20/2012 FINAL PLUS Not Available
3/20/2012 DELDOT APPROVAL LETTER Not Available
3/20/2012 SUBAQUEOUS LANDS PERMIT Not Available
3/20/2012 OFFICE OF AERONAUTICS APPROVAL Not Available
3/20/2012 FIRE MARSHAL APPROVAL RCV'D Not Available
3/20/2012 SCHOOL CERTIFICATION LETTER Not Available
3/20/2012 ARMY CORPS PERMIT APPROVED Not Available
3/20/2012 CRITICAL NATURAL AREA APPROVAL Not Available

Reviews

Review Type Status
INITIAL MAPPING REVIEW Conditional Approval
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
HISTORIC REVIEW EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Incomplete
SEWER CAPACITY AT EXPLORATORY Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
SEWER DESIGN AT EXPLORATORY Conditional Approval
EXPLORATORY REVIEW BY PLANNING Incomplete
TRAFFIC COMPLIANCE REVIEW Incomplete
ENG: EXPLORATORY REVIEW Conditional Approval