Project # 20120061

SUBDIVISION LAND DEVELOPMENT
East side of Kings Grant Road, 350 feet south of Old Lancaster Pike. Rezone and reconfigure tax parcel 08-013.10-209 and 08-013.10-210 from NC21 to ST to create a 6 single family detached and 39 single family attached homes subdivision. NC21 to ST Zoning. CD 3. Mill Creek Hundred
CCS FARMS LLC
RECORDED/RESOLV
BRADFORD S SHOCKLEY
JOHN GYSLING

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Board Recommendations and Input

+
  Legal Agreements and Documents

+
  Miscellaneous Documents

+
  Public Comments

+
  Records Relating to Proceedings

+
  Plans

Subdivision Land Development

Planning

No
3/28/2012
11/26/2014

Ground Floor Area

0
0
0
0

Acres

0
0
0
12
0

Residential Lots

6
39
45

Acreage

12
12

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1500589 OPEN SPACE INSP (RESIDENTIAL) Not Available Incomplete Not Available
1500590 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1500591 RELEASE OF BONDS Not Available Incomplete Not Available
1500592 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available
1500593 ENGINEERING OPEN SPACE AT 50 Not Available Incomplete Not Available
1500594 ENGINEERING OPEN SPACE AT 75 Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
2/2/2012 (ENG) MAJOR EXPLORATORY SKETCH PLAN FEE Paid $1,000.00
2/2/2012 EXPLORATORY SKETCH PLAN FEE Paid $3,000.00
10/23/2013 RESIDENTIAL GRADING PLAN REVIEW Paid $1,500.00
10/23/2013 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $3,825.00
10/31/2013 (ENG) SEWER PLAN FEE Paid $1,500.00
11/1/2013 (LDIA) SEWER INSPECTION FEE Paid $2,485.00
4/9/2014 RESIDENTIAL SWM FACILITY MAINT FUND Unpaid $55,000.00
4/28/2014 AGREEMENT FEE Paid $250.00
10/21/2014 MAJOR RECORD PLAN FEE (RES. SUBDIV) Paid $14,000.00
10/21/2014 (ENG) MAJOR RECORD PLAN REVIEW Paid $2,900.00
10/21/2014 MAJOR RECORD PLAN FEE (REZONING) Paid $3,738.00
12/1/2014 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
2/2/2012 DEVLOPERS AFFIDAVIT 11/17/2014 COMPLETED
2/2/2012 DELDOT APPROVAL LETTER 9/3/2014 APPROVED
2/2/2012 REQ PER SEC 10.3.4.4 OF DSSR 3/5/2012 REPORT ISSUED
2/2/2012 PRE-APPLICATION CONFERENCE 2/10/2012 APPROVED
2/2/2012 REZONING ORDINANCE INTRO 11/17/2014 COMPLETED
2/2/2012 FINAL PLUS 10/21/2013 APPROVE AS AMENDED
2/2/2012 WATER CERTICATION RECEIVED 10/21/2014 APPROVED
2/2/2012 FIRE MARSHAL APPROVAL RCV'D 10/21/2014 APPROVED
2/2/2012 SIGNED AFFIDAVIT FOR POSTING Not Available
2/2/2012 SCHOOL CERTIFICATION LETTER Not Available
10/21/2014 PLAN RECORDATION 12/1/2014 APPROVED
10/21/2014 COUNTY COUNCIL REC PLAN APPROV 12/1/2014 APPROVED
10/21/2014 GENERAL MANAGER RECRD PLAN APR 12/1/2014 APPROVED
10/21/2014 LAND DEV IMPROV AGREE RECORDED 10/21/2014 APPROVED
10/21/2014 RECORDER OF DEEDS FEE RECEIVED 11/5/2014 APPROVED
12/1/2014 OUTFALL DATA SHEET RECEIVED Not Available
12/1/2014 75 PERCENT MAINT ESCROW FUND Not Available
12/1/2014 90 PERCENT MAINT ESCROW FUND Not Available
12/1/2014 SANITARY SEWER Not Available

Reviews

Review Type Status
EXPLORATORY REVIEW BY PLANNING Approved
SEWER CAPACITY AT EXPLORATORY Approved
REZONING REVIEW Approved
ENVIRONMENTAL IMPACT ASSESSMNT Conditional Approval
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
OS REVIEW AT EXPLOR SPEC SERV Approved
HISTORIC REVIEW EXPLORATORY Approved
SEWER DESIGN AT EXPLORATORY Conditional Approval
INITIAL MAPPING REVIEW Conditional Approval
TRAFFIC COMPLIANCE REVIEW Approved
ENG: EXPLORATORY REVIEW Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
SPEC SERV FINAL SEWER REVIEW Approved
ENGINEERING CONSTRUCTION PLAN Approved
FINAL MAPPING REVIEW Approved
RECORD PLAN REVIEW Approved
RECORD PLAN SUBMISSION Approved
TRAFFIC REVIEW AT RECORDATION Approved
ASMNT ASSIGNS PARCELS/ADDRESS Approved
OPEN SPACE STATUS REPORT AT 50 Incomplete
NOTIFY APPLICANT PROJECT @ 90% Incomplete
NOTIFY APPLICANT PROJECT @ 50% Incomplete
NOTIFY APPLICANT PROJECT @ 75% Incomplete
INITIATE OPEN SPACE TURNOVER Incomplete
OPEN SPACE STATUS REPORT AT 75 Incomplete
AS-BUILT FOR STORM WATER MNGMT Incomplete