SUBDIVISION LAND DEVELOPMENT
West side of Limestone Road, 281 feet north of Paper Mill Road. Construct 94 assisted living and 91 independent living units. ST Zoning. CD 3. Mill Creek Hundred.
NAUDAIN LYNN B & RAYMOND
RECORDED/RESOLV
Michael J. Bennett
MIKE ANDREW CLENDANIEL

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Board Recommendations and Input

+
  Legal Agreements and Documents

+
  Miscellaneous Documents

+
  Records Relating to Proceedings

+
  Plans

Subdivision Land Development

Planning

No
1/5/2012
2/27/2013

Ground Floor Area

0
0
0
0

Acres

0
0
0
21
0

Residential Lots

185
185

Acreage

21
21

Inspections

Inspection # Inspection Type Scheduled Date Status Completion Date
1314289 OPEN SPACE INSP (RESIDENTIAL) Not Available Incomplete Not Available
1314290 RECORD COMPLIANCE INSPECTION Not Available Incomplete Not Available
1314291 RELEASE OF BONDS Not Available Incomplete Not Available
1314292 FIELD INSPECTION OF FACILITIES Not Available Incomplete Not Available

Fees

Date Applied Description Status Amount
12/27/2011 (ENG) MAJOR EXPLORATORY SKETCH PLAN FEE Paid $1,000.00
12/27/2011 EXPLORATORY SKETCH PLAN FEE Paid $1,000.00
12/27/2011 NON RES SWM FACILITY MAINT FUND Unpaid $1.00
1/5/2012 EXP EXPLORATORY PLAN FEE Paid $2,000.00
6/27/2012 (ENG) STORM WATER MANAGEMENT E&S FEE-RES Paid $5,045.00
6/27/2012 (ENG) SEWER PLAN FEE Paid $1,500.00
6/27/2012 RESIDENTIAL GRADING PLAN REVIEW Paid $2,000.00
6/27/2012 NONRESIDENTIAL GRADING PLAN REVIEW Refunded $1,000.00
7/23/2012 (ENG) MAJOR RECORD PLAN REVIEW Paid $5,680.00
12/4/2012 (LDIA) SEWER INSPECTION FEE Waived $0.00
12/6/2012 RESIDENTIAL SWM FACILITY MAINT FUND Unpaid $14,400.00
12/6/2012 MAJOR RECORD PLAN FEE (RES. SUBDIV) Paid $42,000.00
12/6/2012 MAJOR RECORD PLAN FEE (REZONING) Paid $6,408.00
12/6/2012 (LDIA) SEWER INSPECTION FEE Paid $1,117.50
12/6/2012 AGREEMENT FEE Paid $250.00
12/12/2012 LDIA PROCESSING FEE Paid $250.00
3/4/2013 STORMWATER AS-BUILT PLAN REVIEW FEE Unpaid $250.00

Conditions

Application Date Description Action Date Action Description
12/27/2011 FINAL PLUS 6/27/2012 RECEIVED
12/27/2011 SIGNED AFFIDAVIT FOR POSTING 12/29/2011 RECEIVED
12/27/2011 PRE-APPLICATION CONFERENCE 1/3/2012 APPROVED
12/27/2011 FIRE MARSHAL APPROVAL RCV'D 1/3/2013 RECEIVED
12/27/2011 DELDOT APPROVAL LETTER 1/17/2013 RECEIVED
12/27/2011 WATER CERTICATION RECEIVED 12/6/2012 RECEIVED
6/27/2012 NOI CONFIRMATION RECEIVED 10/10/2012 RECEIVED
12/6/2012 TAX CERTIFICATION REQUIRED 12/6/2012 APPROVED
12/6/2012 LAND DEV IMPROV AGREE RECORDED 1/30/2013 APPROVE AS AMENDED
12/6/2012 PLAN RECORDATION 3/4/2013 APPROVED
12/6/2012 RECORDER OF DEEDS FEE RECEIVED 1/3/2013 RECEIVED
12/6/2012 COUNTY COUNCIL REC PLAN APPROV 3/4/2013 APPROVED
12/6/2012 TAX CERTIFICATION REQUIRED 1/3/2013 APPROVED
12/6/2012 GENERAL MANAGER RECRD PLAN APR 1/31/2013 APPROVED
3/4/2013 75 PERCENT MAINT ESCROW FUND Not Available
3/4/2013 90 PERCENT MAINT ESCROW FUND Not Available
3/4/2013 OUTFALL DATA SHEET RECEIVED Not Available
3/4/2013 SANITARY SEWER Not Available

Reviews

Review Type Status
INITIAL MAPPING REVIEW Conditional Approval
HISTORIC REVIEW EXPLORATORY Approved
SEWER CAPACITY AT EXPLORATORY Approved
ENVIRONMENTAL IMPACT ASSESSMNT Approved
SEWER DESIGN AT EXPLORATORY Approved
TRAFFIC COMPLIANCE REVIEW Approved
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
OS REVIEW AT EXPLOR SPEC SERV Approved
EXPLORATORY REVIEW BY PLANNING Approved
ENG: EXPLORATORY REVIEW Conditional Approval
PLANNING CONSTRUCTION PLAN RVW Approved
MAINTENANCE DECLARATION REVIEW Approved
LANDSCAPE PLAN REVIEW Approved
SPEC SERV FINAL SEWER REVIEW Approved
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
ENGINEERING CONSTRUCTION PLAN Conditional Approval
WATER MANAGEMENT AGREEMENT Approved
FINAL MAPPING REVIEW Approved
RECORD PLAN REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN SUBMISSION Approved
WATER MANAGEMENT AGREEMENT Incomplete
ASMNT ASSIGNS PARCELS/ADDRESS Approved
OPEN SPACE STATUS REPORT AT 75 Incomplete
OPEN SPACE STATUS REPORT AT 50 Incomplete
AS-BUILT FOR STORM WATER MNGMT Incomplete
INITIATE OPEN SPACE TURNOVER Incomplete
NOTIFY APPLICANT PROJECT @ 75% Incomplete
NOTIFY APPLICANT PROJECT @ 50% Incomplete
NOTIFY APPLICANT PROJECT @ 90% Incomplete
ENGINEERING CONSTRUCTION PLAN Approved
ENGINEERING CONSTRUCTION PLAN Approved
ENGINEERING CONSTRUCTION PLAN Approved
ENGINEERING CONSTRUCTION PLAN Conditional Approval