river photo
Home > Land Use > Project Search > Project Details

Project # 20080272

SUBDIVISION LAND DEVELOPMENT
East side of Kennett Pike (Route 52) north side of Buck Road. Proposal to add 35,949 square feet with associated improvements. CR Zoning. CD 2. Christiana Hundred
GREENVILLE CENTER ASSOCIATES LLC
RECORDED/RESOLV
BRADFORD S SHOCKLEY
MIKE ANDREW CLENDANIEL

+
  Applicant's Submissions and Correspondence

+
  Other Agency Comments, Reviews & Approvals

+
  Planning Review Reports

+
  Engineering Comments and Issues

+
  Studies, Reports and Data

+
  Board Recommendations and Input

+
  Legal Agreements and Documents

+
  Miscellaneous Documents

+
  Procedural Documents

+
  Public Comments

+
  Records Relating to Proceedings

+
  Plans

Subdivision Land Development

Planning

No
3/27/2008
8/28/2013
TAC REVIEW

Ground Floor Area

91476
122864
35949
158813

Acres

6.6
1.84
10.54
0
0

Non-residential Lots

1
1

Fees

Date Applied Description Status Amount
3/28/2008 EXPLORATORY PLAN FEE Paid $500.00
10/17/2008 REVISED EXPLORATORY PLAN FEE Paid $500.00
2/12/2009 NON RES SWM FACILITY MAINT FUND Unpaid $1.00
7/21/2009 PLAN EXPIRATION EXTENSION Paid $50.00
10/26/2009 PRELIMINARY PLAN FEE WITHOUT REZONING Paid $1,500.00
10/26/2009 (ENG) PRELIMINARY PLAN REVIEW FEE Paid $975.00
3/7/2011 PLAN EXPIRATION EXTENSION Paid $50.00
3/28/2011 PLANNING RESUBMISSION FEE Paid $750.00
3/28/2011 ENGINEERING RESUBMISSION FEE Paid $750.00
6/21/2011 MAJOR RECORD PLAN FEE (NONRES LAND DEV) Paid $12,190.00
6/21/2011 (ENG) RECORD PLAN REVIEW FEE Paid $2,317.00
6/21/2011 (ENG) STORM WATER MANAGEMENT E&S FEE Paid $2,475.00
6/21/2011 (ENG) SEWER PLAN FEE Paid $750.00
6/21/2011 AGREEMENT FEE Paid $250.00
6/21/2011 (ENG) GENERAL DEVELOPMENT NON RES FEE Paid $1,000.00
6/21/2011 (LDIA) SEWER INSPECTION FEE Paid $740.00
1/3/2013 PLAN EXPIRATION EXTENSION Paid $50.00
1/3/2013 PLAN EXPIRATION EXTENSION Paid $50.00
6/3/2013 LDIA PROCESSING FEE Paid $250.00

Conditions

Application Date Description Action Date Action Description
3/28/2008 SIGNED AFFIDAVIT FOR POSTING 4/1/2008 APPROVED
3/28/2008 PRE-APPLICATION CONFERENCE 4/8/2008 APPROVED
10/26/2009 DRAFT TAC REPORT 12/17/2009 APPROVED
10/26/2009 TAC REVIEW AT PLAN BOARD MTG 1/13/2010 APPROVED
10/26/2009 FINAL TAC REPORT 1/26/2010 APPROVED
10/26/2009 SIGNED AFFIDAVIT FOR POSTING 1/13/2010 APPROVED
10/26/2009 DELDOT COMMENTS RECEIVED 1/26/2010 APPROVED
10/26/2009 NOTIFICATION OF TAC AGENCIES 12/15/2009 APPROVED
6/21/2011 RECORDER OF DEEDS FEE RECEIVED 7/11/2013 RECEIVED
6/21/2011 FIRE MARSHAL APPROVAL RCV'D 6/6/2013 APPROVED
6/21/2011 LAND DEV IMPROV AGREE RECORDED 7/19/2013 APPROVED
6/21/2011 WATER CERTICATION RECEIVED 6/25/2013 APPROVED
6/21/2011 NOI CONFIRMATION RECEIVED 6/25/2013 COMPLETED
6/21/2011 DELDOT APPROVAL LETTER 7/10/2013 RECEIVED
6/21/2011 COUNTY COUNCIL REC PLAN APPROV Not Available
6/21/2011 PLAN RECORDATION Not Available
6/21/2011 GENERAL MANAGER RECRD PLAN APR Not Available

Reviews

Review Type Status
EXPLORATORY REVIEW BY PLANNING Waived
HISTORIC REVIEW EXPLORATORY Approved
INITIAL MAPPING REVIEW Conditional Approval
SEWER DESIGN AT EXPLORATORY Approved
STAFF MEETING Conditional Approval
EXPLORATORY SUBMISSION REVIEW Approved
ENG: EXPLORATORY REVIEW Conditional Approval
SEWER CAPACITY AT EXPLORATORY Approved
PRELIMINARY TRAFFIC ANALYSIS Conditional Approval
TRAFFIC IMPACT STUDY Conditional Approval
OS REVIEW AT EXPLOR SPEC SERV Approved
OS REVIEW AT EXPLOR SPEC SERV Approved
PRELIMINARY SUBMISSION REVIEW Approved
PRELIMINARY PLAN REVIEW Waived
SEWER DESIGN AT PRELIMINARY Conditional Approval
OS REVIEW AT PRELIM SPEC SERV Approved
PUBLIC SAFETY REVIEW AT PRELIM Conditional Approval
SEWER CAPACITY AT PRELIMINARY Approved
TRANSPORTATION COMPLIANCE REV Approved
ENVIRONMENTAL IMPACT ANALYSIS Conditional Approval
ENGINEERING PRELIMINARY REVIEW Conditional Approval
RECORD PLAN SUBMISSION Approved
ENGINEERING RECORD PLAN REVIEW Conditional Approval
SPEC SERV FINAL SEWER REVIEW Approved
PUBLIC SAFETY REVIEW AT RECORD Conditional Approval
MAINTENANCE DECLARATION REVIEW Conditional Approval
FINAL MAPPING REVIEW Approved
TRAFFIC REVIEW AT RECORDATION Approved
RECORD PLAN REVIEW Approved
LANDSCAPE PLAN REVIEW Approved
ENGINEERING RECORD PLAN REVIEW Conditional Approval
ENGINEERING RECORD PLAN REVIEW Conditional Approval
ENGINEERING RECORD PLAN REVIEW Approved
EXPLORATORY REVIEW BY PLANNING Conditional Approval
PRELIMINARY PLAN REVIEW Approved